San Diego-based Sempra Energy is targeting summer of 2025 as the commercial operations date for its 3.25 mtpa (0.43 Bcf/d) nameplate capacity Energía Costa Azul (ECA) LNG Phase 1 project, located in Ensenada in Baja California, Mexico. The project will source U.S. gas.
Gas will be delivered to ECA LNG Phase 1 with the completion of the GRO pipeline expansion, which will have a capacity of 0.5 Bcf/d, Sempra said Feb. 27 in its fourth quarter 2023 earnings release.
Sempra’s Houston-based affiliate Sempra Infrastructure has an 100% ownership interest in the pipeline.
ECA Phase 1 will consist of one 3.25 mtpa train with an initial offtake capacity of 2.5 mtpa (0.33 Bcf/d), according to Sempra Infrastructure, which has an 83.4% working interest in the project. France’s TotalEnergies has a 16.6% working interest in the project.
ECA LNG Phase 2
A second phase of ECA LNG is also planned and will have 12 mtpa of export capacity.
Sempra Infrastructure has already signed a heads of agreement with Houston-based ConocoPhillips and memorandums of understanding with TotalEnergies and Japan’s Mitsui.
ECA LNG Phase 2, like ECA LNG Phase 1, will also source gas from the U.S.
Recommended Reading
OTC: Will More Electrical Demand Bring Energy Debate Back to Reality?
2024-05-06 - Energy experts, including Scott Tinker, touted the importance of discussing the environmental and economic impacts of moving energy forward at the 2024 Offshore Technology Conference.
Bill Gates: ‘A Heroic Effort’ is Beginning, but Climate Goals Still Won’t be Hit
2024-03-26 - Bill Gates said during CERAWeek by S&P Global that the energy transition was picking up speed but still wouldn’t be able to achieve the climate goals established under the Paris Agreement of 2015.
CERAWeek: NextEra CEO: Growing Power Demand Opportunity for Renewables
2024-03-19 - Natural gas still has a role to play, according to NextEra Energy CEO John Ketchum.
Avangrid Begins Construction on its First California Solar Farm
2024-04-10 - Avangrid’s Camino Solar project will generate 57 megawatts of power, the equivalent of the power needs of about 14,000 U.S. homes.
Solar Panel Tariff, AD/CVD Speculation No Concern for NextEra
2024-04-24 - NextEra Energy CEO John Ketchum addressed speculation regarding solar panel tariffs and antidumping and countervailing duties on its latest earnings call.